Purge plus Sealing
Stop specks, save at once
Purge and seal with ASACLEAN to stop black specks returning — less carbonized burn, downtime and real hidden line costs.
Deep dive into hidden costs (Hidden Costs)
Why do low-grade compounds or unfinished purges cost more than you think?
No seal / low-power purging compound
*Assumptions: 200-ton injection machine, 9 purges per month, 1,000 THB per hour opportunity cost.
- Compound plus scrap (12.5 kg x 80 THB x 9 times)9,000 THB
- Speck defects (45 pcs x 25 THB x 9 times)10,125 THB
- Machine-stop time (5.25 hrs x 1,000 THB)5,250 THB
- Screw-pull opportunity loss (3.5 hrs x 1,000 THB)3,500 THB
Total hidden cost per month
With ASACLEAN plus sealing
*Only 4 purges per month, total purge time under 1 hour, no screw pull.
- ASACLEAN compound (1 kg purge plus 0.5 kg seal)1,320 THB
- Speck defects (0 pcs)0 THB
- Machine-stop time (slashed)-
- Screw-pull opportunity loss (none needed)0 THB
Total cost per month
Short picture
200-ton injection machine uses 1 kg ASACLEAN purge plus 0.5 kg seal, averaging just 330 THB per time.
- 4 purges per month totals only 1,320 THB per month.
- Total purge time under 1 hour.
- Jobs open with zero black-speck defects.
Hard truth
Old-method purging may look low cost per kilo But adding defects, scrap, stoppage and screw pulls, true cost can hit 27,875 THB per month versus ASACLEAN saving over 26,555 THB per month per machine.
Savings in every production dimension
A good compound saves not just material cost but time, scrap, labor and production opportunity — ASACLEAN returns machines to good parts faster, cuts specks and unseen line costs.
ASACLEAN shutdown sealing procedure
Sealing means holding ASACLEAN in the barrel during stops after old resin is purged — cutting leftover-resin contact with oxygen and heat, the key carbonization-and-burn mechanism.
Standard procedure
- 1Discharge old material fullyAfter production, discharge molding materials first for effective purging.
- 2Feed ASACLEAN and rotate the screw to purgePurge across until old resin is displaced with no old color or material bleeding.
- 3Visual checkConfirm old material is out, then enter sealing.
- 4Feed ASACLEAN to sealHold ASACLEAN in barrel and nozzle during the stop as a barrier layer against oxygen reaching leftover resin.
- 5Meter full shot volumeMeter full shot volume per machine terms to hold ASACLEAN in position.
- 6Stop the machine / switch off heatersSwitch off or lower temperature at stops to cut stored-heat and resin-degradation risk.
- 7New start: heat up and discharge before productionDischarge ASACLEAN clean, then feed next material and verify part quality.

No seal: burn stuck on screw
Sealed: ASACLEAN leaves no gapsRoutine purging and sealing versus resin degradation
Without purging and sealing, resin degradation climbs until burnt residue flakes as specks — routine purging holds degradation low; sealing keeps it inside ASACLEAN-purgeable bounds.
If you do nothing
Resin degradation climbs to very high, baked-on burn flakes as specks — major strip-down (overhaul) needed.
Routine purging
Purge on schedule while residue still releases easily; degradation stays low, never accumulating to quality problems.
Sealing
Hold ASACLEAN during stops against oxygen; degradation stays inside ASACLEAN-purgeable bounds, near-zero screw residue.
Concept adapted from the Asahi Kasei document Conceptual view of contamination generation mechanism in the barrel — conceptual illustration, not values measured on every machine.
Outcomes production teams want
Cut residue before trouble
Run ASACLEAN on PM (preventive maintenance) rhythm to cut burn and holdup before quality problems.
Cleaner screws
Concept from documents — cleaner screws after purging, less flaked contamination next jobs.
Oxygen protection
After purging, hold ASACLEAN in the barrel against oxygen, slowing leftover-resin degradation.
Worked example
Purge with just 1 kg ASACLEAN and 0.5 kg seal, within 10 minutes, fewer specks from job start, fewer mid-week repeat purges. Core idea: never judge purging-compound price per kilo — total scrap, stoppage and screw-pull risk too.
Technical data and fitting grades should be checked against the Technical Data Sheet and ASACLEAN specialists per real machine terms before use. Example figures are estimates under specific assumptions, not guaranteed results for every machine.
Want your machine to open jobs with zero specks?